Skip to Content

SLS delays and what actually happened

SLS delays and what actually happened
The Space Launch System was supposed to be America’s ticket back to the Moon. Built by NASA with major contractors like Boeing, Aerojet Rocketdyne, and Northrop Grumman, the SLS was pitched as a powerful, reliable super-heavy lift rocket that would carry astronauts beyond low Earth orbit for the first time since Apollo. But instead of dominating headlines with lunar flybys and crewed missions, the SLS became a symbol of delay, cost overruns, and technical headaches. If you followed the Artemis program over the past decade, you saw launch dates slip from 2017 to 2018 to 2020 to 2021, and finally to a successful but messy Artemis I launch in late 2022. What actually happened? The answer is a mix of bad contracting, outdated engineering culture, and a rocket design that was never optimized for the modern era.

The SLS was born from political necessity, not engineering brilliance. After the Space Shuttle retired in 2011, NASA had no heavy-lift capability. Congress, worried about losing jobs in key districts, directed NASA to build the SLS using Shuttle-derived hardware. That meant using leftover Shuttle main engines, solid rocket boosters built from Shuttle designs, and a core stage that mimicked the Shuttle’s external tank. The goal was to save money and time by reusing proven technology. In reality, it locked NASA into a 1970s architecture that was expensive to manufacture and hard to test. The core stage, for example, required a massive new welding tool at the Michoud Assembly Facility in Louisiana. That tool alone took years to qualify, and when it finally worked, the first core stage was delivered years late.

Then came the green run testing fiasco. In early 2021, NASA stacked the Artemis I core stage on the B-2 test stand at Stennis Space Center for a full-duration static fire. The first attempt shut down after just 67 seconds due to a hydraulic issue with the engine steering system. Engineers spent months troubleshooting, replacing a faulty controller, and retesting. That delay pushed the entire Artemis I timeline back by nearly a year. But the green run problems were just a symptom of a deeper issue: the SLS was a bespoke, low-production-rate rocket built by a workforce accustomed to government cost-plus contracts. Every part was custom, every weld inspected like a museum piece, and every schedule slip simply meant more money flowing to contractors.

The Orion capsule, which rides atop the SLS, added its own delays. Built by Lockheed Martin, Orion required extensive modifications after initial thermal protection system issues emerged. During early testing, engineers discovered that the heat shield ablative material, Avcoat, had cracked and eroded more than expected. NASA had to redesign the manufacturing process and retest it. Meanwhile, the European Service Module, built by Airbus, faced supply chain problems and integration headaches. When you combine a troubled rocket with a troubled capsule, you get a schedule that moves right every quarter.

So what did Artemis I actually accomplish? On November 16, 2022, the SLS finally launched from Kennedy Space Center’s Launch Complex 39B. The flight was impressive by any measure. The core stage and boosters performed nearly flawlessly, and the interim cryogenic propulsion stage sent Orion on a trajectory around the Moon. Orion traveled farther from Earth than any human-rated spacecraft in history, looped around the lunar farside, and returned for a splashdown in the Pacific. But the mission also revealed issues. The launch pad, especially the mobile launcher, suffered unexpected damage from the rocket’s exhaust. The heat shield again showed more char loss than models predicted, prompting a year-long investigation. And the cost of that single uncrewed mission? Roughly four billion dollars.

Now, Artemis II, the first crewed flight, has been delayed again. Originally targeted for late 2024, it now slips to no earlier than late 2025, and some insiders whisper 2026. The heat shield problem is the main culprit. Engineers discovered that during reentry, gases built up inside the Avcoat material, causing it to crack and shed differently than expected. NASA wants to understand exactly what happened before risking a crew. That means more testing, more analysis, and more schedule slips. On top of that, the SLS rocket for Artemis II, a new core stage, still needs to complete its own green run testing at Stennis. Nothing moves fast in the SLS program because nothing is designed to move fast.

The big question is whether the SLS is worth it. Critics point out that commercial rockets like SpaceX’s Starship and Blue Origin’s New Glenn promise similar capabilities for a fraction of the cost. Starship, for example, is designed for full reusability, which could drive per-launch costs down dramatically. But the SLS is not a commercial rocket. It is a government program built to preserve jobs and maintain industrial base capabilities. That means it will keep flying, at least for the next few Artemis missions. The real test will come if Starship proves reliable and affordable. At that point, NASA will have to decide whether to keep spending billions per launch or pivot to a more modern, competitive vehicle.

For now, the SLS story is a cautionary tale about what happens when you build a rocket by committee. You get a machine that works, eventually, but only after years of delays, billions in overruns, and a design that looks backward instead of forward. The next launch will happen, but don’t hold your breath for a schedule change.

Space News

Latest Articles

New rockets, upcoming launches, and the stories shaping humanity's push off this planet. No astronomy degree required.